Client

Ministry of Transport

Construction Cost

125 million SAR

Services Performed

  • Preliminary Design,
  • Final Design,
  • Preparation of Tender Documents.

Project Components

  • 12 km. 3 lane carriageway
  • 2 grade seperated I/C’s
  • Relevant hydraulic

structures

Description

King Abdullah Road is a major network element of Qassim-Madinah-Rabigh Expressway starting from State Road 60 continuing till the junction of Road 6361 and terminated at the junction of King Abdullah Inner Ring Road.The project comprises the studies of the alignment selection, preliminary / final designs and the preparation of the tender documents for 12 km / 3-lane dual carriageway with a design speed of 100 km/hr including 2 grade seperated new I/C. The scope comprises the detailed design of the storm drainage works and its relevant structures in addition to the crossing and wadi bridges alonge road alignment.