Client
Ministry of Transport Construction Cost
70 million SAR
Services Performed
- Corridor / Alignment Selection Studies,
- Preliminary & Final Design Studies,
- Preparing of Tender
Documents.
Main Project Components
- 65 km. state road,
- 1 wadi bridge,
- 3 at-grade intersections,
- Relevant minor hydraulic structures.
Description
Alignment selection, preliminary & final design studies, preparation of tender documents for the 53km 1 lane dual carriageways with a design speed of 80km/hr. İncluding 6 at grade I/C.’s and 9 km. of 1 lane dual carriageways being one of the major components of the project.