![](https://creativengineering.us/wp-content/uploads/2019/09/22.jpg)
Client
Ministry of Transport Construction Cost
45 million SAR
Services Performed
- Preliminary / Final Design,
- Signing & Marking,
- Geotechnical Studies,
- Drainage measures,
- Structural Design,
- Preparation of Tender Documents.
Project Components
- 5 km. of dual access road,
- 1 grade-seperated interchange
- 1 multi-span I/C bridge.
Description
This is located at the east of Madinah, on Qassim-Madinah road. The Al-Aqul Primary Road is serving the traffic between the expressway and the secondary roads. The diamond type Al-Aqul Interchange is the major element of the primary road network, this comprises also a multi-span bridge. The primary road lays on relatively flat terrain and have a design speed of average 100 km/hr.