Client:-
Smart Villages Co.
Services performed:-
Project Management Services during the Construction phase of the club
Project components:-
70,000.00 S.M. of land containing:-
Semi-Olympic swimming pool Full Size football field with 4 lanes track 6 hard core tennis field 1 multi-purpose field Sports building containing gym, spa & 2 squash courts, & 1 social building
Description:-
The project was implemented in 18 calendar months including design and tender phases.
The project has been divided into 7 packages distributed over 7 contractors for cost reduction purposes, the coordination process among the 7 contractors was the main duty of the project manager.
Reviewing the contractors’ invoices and approving it for quick payment was the key to the success of this project.